Agile PMI-ACP Domain 5
▌Introduction
Evolving
plan (逐步形成之計畫) from initiation to closure,
based on
1.
Goal
2.
Values
3.
Risks
4.
Constraints
5.
Stakeholder feedback
6.
Review findings
▋Difference between
Predictive planning and Adaptive planning
▋Predictive Planning
1.
Project is successful when the plan is met, and the
deliverables are as planning.
2.
Plan depends on the stability of requirements.
3.
Process first.
▋Adaptive Planning
1.
Requires evolutionary design.
2.
People first.
▌Concept
▋Team
1. Maintain a prioritized backlog.
2. Have close collaboration with the
customer.
3. Deliver a working, tested increment
after each iteration.
4. Welcome to change and respond.
5. Consistent staff.
▋R&R (Roles and
Responsibilities)
Role
|
Responsibility
|
PO/Customer
|
1. Define and prioritize requirement
2. Define release goal and iteration
goal
|
(Development)
Team
|
1. Define velocity
2. Co-work with PO/Customer
|
Scrum
master/
XP Coach
|
1. Check if team follow Agile process
2. Support the team’s need
|
▌Value-based
analysis
▋Delivery
MMF/MVP
▋MMF:
Minimum Marketable Feature
A release is a collection of MMFs.
Objective: Selling
▋MVP:
Minimum Viable Product
MVP is a product which has just enough features to gather validated learning and continued development
Objective: Learning from market
▌Innovation games
Goal:
1.
Identify customer requirement
2.
Improve retrospectives
3.
Prioritize backlogs
4.
Create better release plans
▋Design a Product Box
▋Me and my shadow
1. Identify customer's hidden needs
2. Watch what they do and ask why
3. Record key activities by camera or ...
▋Speed boat
1. The boat is
the System
2. The features
they dislike are Anchors
▋Remember the Future
1. Understand the customer's definition of success
2. Customer write down what they image the product's future
▋Buy a feature
1. Create a list of features with a price
for each. Price is based on development costs, customer value.
2. By customer buying the feature, we can
prioritize the features (product backlog)
▋Prune the product tree (For better
release plans)
Develop better release plans to shape the product for market.
Develop better release plans to shape the product for market.
▋Timebox planning
▋Rolling wave planning and Progressive
elaboration
As the project progress, we can identify the risks, assumptions and milestones more reliable and clear.
As the project progress, we can identify the risks, assumptions and milestones more reliable and clear.
▋Exploratory testing (Learn from
testing it)
Test as experiments.
▌Agile Estimation
▋Who should do the estimation
Development team
Development team
▋What is Story Point
1. A number how hard a
User Story is, related to complexity, unknowns and efforts
2. Usually Fibonacci
series (1,2,3,5,8,13,21,34,45) or a modified one (1,2,3,5,13,40,100)
3. Relative, not actual
working time.
▋How to estimate
1. Find a baseline story
2. Use one of the
following estimation techniques
n
Planning poker
n
T-shirt sizing
n
Wideband Delphi
n
Ideal time
n
Affinity estimating
n
Velocity
▌ Planning Levels
▋Product Vision
1. Elevator statement
2. Product box
▋Product Roadmap
1. Communicate
2. Determine when releases are needed
3. Determine what functions are sufficient for each release
4. Focus on business value from the release
▋Release Plan
1. Release with Date, Theme, Planned feature set
2. Typical interval: 2 - 4 months
▋Iteration Plan
Iteration 0: Spike, setting environment
Last iteration: Fixing bugs, refactoring...
▋Daily Commitment
1. Iteration backlog to Task, estimate every task
2. A feature is not done until it is tested, meet the DoD and accepted by PO
3. Daily stand-up meetings
1. Elevator statement
2. Product box
▋Product Roadmap
1. Communicate
2. Determine when releases are needed
3. Determine what functions are sufficient for each release
4. Focus on business value from the release
▋Release Plan
1. Release with Date, Theme, Planned feature set
2. Typical interval: 2 - 4 months
▋Iteration Plan
Iteration 0: Spike, setting environment
Last iteration: Fixing bugs, refactoring...
▋Daily Commitment
1. Iteration backlog to Task, estimate every task
2. A feature is not done until it is tested, meet the DoD and accepted by PO
3. Daily stand-up meetings